The Setweek programme: five checkable stages.
A typical programme runs 33 weeks from the day your deposit clears to handover. Every job gets its own programme in the contract.
The 33-week programme
- Weeks 0–8 — Design. Design detail, engineering and certifier approvals, then design freeze.
- Weeks 8–25 — Factory build. Independent third-party quality inspections at frame (about week 16) and at final factory inspection (about week 25). Reports are shared with you.
- Weeks 25–30 — Delivery to site. Foundations go in during weeks 28–30, timed to delivery.
- Week 30 — Crane and set. The modules are craned into place.
- Weeks 30–33 — Finish and handover. Services, finishing, certificates, final inspection and handover.
"Installed in a week" refers to the on-site set and install of the modules, not the whole programme.
How your install week is fixed
- Two fortnight windows at feasibility.
- A reserved window when your deposit clears.
- A named week, in writing, once delivery is booked.
- A named day 21 days out, once the slab and site access are confirmed.
Payments tied to stages you can check
- 30% at signing
- 17% at frame inspection
- 25% at final factory inspection
- 25% before modules are dispatched to site
- 3% at handover
Nothing is ordered until your deposit clears. Commercial clients use this schedule; homes for owner-occupiers use a separate, lawyer-approved schedule.
Where modular doesn't fit
A brief that keeps moving, a street a module can't travel, a one-off building, or an in-situ podium or core, which is still a normal building site. We'll tell you at feasibility.
See how the programme fits your site.
Book a feasibility Read the FAQ
Setweek by Construction Industry Professionals. Setweek is a product name of Construction Industry Professionals Pty Ltd · ABN 98 621 384 405 · QBCC 15198532 · Queensland projects only. Mobile 0423 329 901 · dan@CIPproperty.com.au